Vermilion 313

VR 313 Project

  • 4 pile platform in 240' water 
  • 8 Conductors
  • Toppled by Hurricane Rita

OPS Contributions

  • Developed project timeline, afe, and diving/rov inspection program 
  • Prepared underwater salvage plan based on Photon Imaging results
  • Competitively bid and managed jacket, deck, and equipment salvage operation
  • Supplied onsite inspection and company representation for the duration of the project
  • Instrumental in safety program development including JSAs and BBS Observations
  • Critically reviewed and approved contractor invoices